How we build · Miami-Dade, Broward, Palm Beach
From the first site visit to the final walkthrough: a superintendent who confirms the next steps every week, and a client portal with photos, inspections and invoices.
How we build
The home construction process with Florida Home Build has eight steps, from a site visit before any contract to a walkthrough of every system before you move in. You work with one contractor, and your project manager is your contact from the first meeting.
After you send a request, we contact you within a day. Then we visit your lot or property and walk you through a line-by-line estimate, before any contract is signed.
Who is on your project:
The same eight steps apply to every project. For a renovation or a condo, what comes first and what the schedule counts from change, and the table further down shows how. The typical length of each phase of a new home is in the timeline below.
Timeline
A site visit before any contract, a line-by-line estimate and a meeting with your project manager.
Plans and selections, tied to the budget and the price cap.
City and county permits, inspections and association submissions are on us.
Your superintendent confirms the next steps every week, with photos and inspections in your client portal.
Usually 28–36 months from the first meeting to move-in. These are estimates, not promises: rain, inspections and permit queues move dates, and you see every change in the portal the week it happens. On average the build takes 2–4 hours of your time per week.
Get a timeline for my lotEight steps
Most steps end with something you can check: a line-by-line estimate, a contract, a set of plans, a permit, a photo report, an inspection result, a handover package. The client portal holds the schedule, selections, photos, inspection results and invoices.
We visit your lot or property before any contract, walk you through a line-by-line estimate and introduce your project manager.
You sign cost plus a fixed fee, with a maximum price. How the money works is on the pricing and terms page.
Plans, finishes and fixtures are settled against the budget. Architect and designer fees are not part of the construction price.
We file and track the city and county permits and, in a condo, the association submission. Permit fees are not part of the construction price.
Your superintendent takes charge of the site, and the schedule is in your client portal.
Every week the superintendent confirms the next steps with you. Photos and inspection results land in your portal, and each subcontractor bid, change and invoice sits in the shared budget tracker.
City and county inspections continue to the end. In Miami-Dade a certificate of occupancy is required before you move into a new or reconstructed home.
We walk the house with you and show how each system works, then hand over as-built drawings, manuals, a maintenance schedule and manufacturer warranties in your name. The 3-year warranty on the work has its own page.
Out of state
By project
The eight steps are written for a new home. For other projects, what comes first and what the schedule is counted from change. The last column shows how the time is counted for each project, and the estimates in it are not promises.
| Project | What comes first | What changes | How the time is counted |
|---|---|---|---|
| New home on your lot | Site visit, budget and design | All eight steps in order, ending with a certificate of occupancy | An estimated 28–36 months from the first meeting to move-in |
| Whole-home renovation | Site visit and a line-by-line estimate | The schedule starts from permits and material delivery | After permits are issued and materials arrive |
| Condo renovation | The association submission | We prepare and file it before work starts | An estimated 3–8 months, counted the same way |
| Waterfront home | A review of the site | Flood-zone rules may join the permit step | Set after the site review |
| Seawall or dock | A review of the site | Marine permits are part of the project; the seawall page has the details | Set after the site review |
| Commercial build-out | Permits for the space | A certificate of occupancy, then a certificate of use for the business | Scheduled by project |
After the keys

The term and the list of exclusions are written in your contract, not explained later.
As-built drawings, manuals, a maintenance schedule and manufacturer warranties registered in your name.
We walk the house with you and show how each system works before you move in.
Home maintenance by arrangement, with the same team that built it.
FAQ
At Florida Home Build the process has eight steps: site visit and budget, contract, design and selections, permits, start of work, weekly building, the final stretch with inspections, and the walkthrough and handover. Each one is explained above. For a general guide to building in the state, read steps to building a house in Florida.
We contact you within a day. Then we visit your lot or property, walk you through a line-by-line estimate and introduce your project manager, all before any contract is signed.
On average the build takes 2–4 hours of your time per week. You confirm selections and approve each stage, on site or in the client portal.
We do. City and county permits, inspections and condo association submissions are part of the work. Permit and other fees are not in the construction price, and the pricing and terms page lists everything the price leaves out.
A project manager from the first meeting and a superintendent who runs the site, both from the one contractor on your contract. The list near the top of the page shows who does what.
For a new home, usually 28–36 months from the first meeting to move-in, and the phases partly overlap. These are estimates, not promises. The full breakdown covers each phase and what moves the dates.
The steps are the same, but the schedule is counted from the day permits are issued and materials arrive, and a condo adds an association submission at the start. A condo renovation is estimated at 3–8 months; for a house renovation the time is counted from the same two events.
We walk the house with you and show how each system works, then hand over as-built drawings, manuals and a maintenance schedule. A new home gets its certificate of occupancy before move-in. The last of the four stage payments is described on the pricing and terms page.